17 x 24.5m, the ceiling slab above the main entrance of the new of the new Kantonsspital Baden (KSB). protrudes. There is a circular aperture to accommodate a tree in the cantilever, and offices will later be installed on the airy ceiling slab. The demands on statics and building construction logistics were correspondingly high. For the 23-metre-long steel lattice girder, special transportation was required at 5 o’clock in the morning. The 60-tonne pneumatic crane required for the work, in turn, required the reinforcement the underground Spitaltunnel (hospital tunnel) connections. All this is set against the small number of 4 – because, that was the time needed to complete the installation work. Confirm hereby thanks the great KSB (Baden Cantonal Hospital) building construction site team!